Business Requirements Specification
WEIM FAB Enhancements
Document Version: 1.0
Current Version Date: 5/31/2024
Revision History
Date
Version
Description
05/31/2024
1.0
Document created
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 2 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
Table of Contents
1 Introduction ................................................................................................................................... 3
1.1 Purpose .................................................................................................................................. 3
2 Details of Business Need/Problem................................................................................................... 4
2.1 Description .............................................................................................................................. 4
3 Project Impact Assessment (IA) ...................................................................................................... 6
3.1 Business Practice Manuals (BPM)............................................................................................... 6
3.2 Tariff Business Ownership ......................................................................................................... 6
3.3 Other ...................................................................................................................................... 6
4 Business Requirements .................................................................................................................. 8
4.1 General: FAB Enhancements ..................................................................................................... 8
4.1.1 Business Requirements: Congestion Management Full Transparency........................................... 8
4.1.2 Business Requirements: External WEIM Commitment Override ................................................ 17
4.1.3 Business Requirements: System NET ITC Definitions .............................................................. 19
4.1.4 Business Requirements: Dynamic ETSR Limits Safety Net ..................................................... 20
Appendix C: Display Mockup and Report Questionnaire........................................................................ 21
Resource Congestion Mockup (BRQ010, BRQ011, BRQ012) ................................................................... 21
Binding Transmission Constraints Flowgates Mockup (BRQ013, BRQ014, BRQ015) ................................... 22
Binding Transmission Constraints Nomograms Mockup (BRQ016, BRQ017, BRQ018)................................. 23
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 3 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
1 Introduction
1.1 Purpose
This document describes high level business requirements to support the WEIM FAB
Enhancements initiative.
The project aims to primarily improve market robustness, performance, and the technology foundation for
system grid reliability by updating functionality and interfaces to reduce workarounds, automating manual
processes and addressing minor defects or functionality enhancements identified by the business
units.These enhancements focus primarily on CAISO and WEIM customer
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 4 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
2 Details of Business Need/Problem
2.1 Description
Business Opportunity/Problem Statement:
What:
WEIM FAB Enhancements consist of three enhancements and
one improvement. This project aims to improve RTM robustness,
minimize Market Isolations, modernize tools for Support Control
Center, provide accurate, accessible, and clear information to
ensure customer preparedness and to deepen understanding
about the reliability needs of the grid.
WEIM Fab-Enhancements:
1) Congestion Management Full Transparency
2) Hourly Base ETSR Schedule Redundancy (project, RTM
payload). Note: This item is being pursued as its own stand
alone project.
3) External WEIM Commitment Override
4) Dynamic ETSR Limits Safety Net
5) System Net ITC Definitions
Why do we have this
opportunity/problem:
Primary business case is for reliability, control center
improvements, situational awareness and transparency.
The following are reasons for delivering these enhancements.
1) Congestion Management Full Transparency. Lack of
situational awareness to WEIM BA Operators is a reliability
risk. This enhancement will help address seams issues that
multiple WEIMs and RCs have been dealing with.
2) Hourly Base ETSR Schedule Redundancy. Without this
enhancement there will be prolonged Market Disruptions,
Market Isolations, Settlement implications and most importantly
very high risk to reliability for many WEIMs. Due to the
complexity of this item it is slated as its own project instead of
being included here as an enhancement.
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 5 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
Business Opportunity/Problem Statement:
3) External WEIM Commitment Override. This enhancement
streamlines WEIM entities with the ability to directly enter
WEIM commitment overrides.
4) Dynamic ETSR Limits Safety Net. This enhancement
addresses a reliability concern. Note: This item is still being
scope will be included with more detail in the next External
BRS posting.
5) System Net ITC Definitions.System Net ITC definitions create
the most effective and fastest way for WEIMs to manage
ETSRs in the RTM.
Who does this
opportunity/problem
impact:
WEIM entities, WEIM BA Operators (CAISO included), RTMO, and
Customer Service.
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 6 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
3 Project Impact Assessment (IA)
3.1 Business Practice Manuals (BPM)
BPM
Description of Impact(s)
Market Operations
Update to reflect that WEIM operators
performing commitment overrides themselves
instead of CAISO performing this in BAAOP.
3.2 Tariff Business Ownership
Tariff Section
Business Owner
Not Impacted
Not Applicable
3.3 Other
Impact
Description (optional)
Market Simulation
No
Market Participant Impact
See Customer Readiness below.
External Bid Publication
No
Customer Readiness Impact
Yes, see below.
External Communication Needed
Yes
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 7 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
Impact
Description (optional)
Transmission Resource Congestion
External WEIM Commitment Override
System Net ITC Calculations
Dynamic ETSR Limits Safety Net
External Onboarding and
Maintenance
No
External Training
Yes
External Computer Based Training
Yes
Policy Initiative
No
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 8 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
4 Business Requirements
The sections below describe the business processes and the associated business requirements involved
in the project. These may represent high-level functional, non-functional, reporting, and/or infrastructure
requirements. These business requirements directly relate to the high-level scope items determined for
the project.
4.1 General: FAB Enhancements
4.1.1 Business Requirements: Congestion Management Full Transparency
ID#
Business Feature
Req.
Type
Potential
Application(s)
Impacted
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 9 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
FAB
BRQ010
Transmission Resource Congestion
Within System (RTM), the RTD, RTPD, and
STUC UIs must display to CAISO and WEIM
Operators their BAA’s resources in the
Congested Resources” table (left side).
Note: UI updates only for displaying existing-in-
application data that is not currently shown.
Note: See Mockup in Appendix C.
Note: This requirement applies to any WEIM BAA
with existing access to RTM. No new access
provisioning needed in AIM, no updates to roles
needed in AIM.
Warning: “WEIM Operators are responsible for
ensuring this information is handled within
their own organizations consistent with
FERC’s Standards of Conduct for
Transmission Providers. The CAISO is not
requiring any additional attestations from
WEIM Operators or imposing additional
access controls within the BAAOP system.
Core
RTM RTD
RTPD
STUC
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 10 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
FAB
BRQ011
Transmission Resource Congestion
Within System (RTM) in the RTD, RTPD, and
STUC UIs, must have functionality for CAISO and
WEIM Operators to select any of their resources
from the left side of the table and on Constraints
causing Congestion” table (right side).
Note: UI updates only for displaying existing-in-
application data that is not currently shown.
Note: See Mockup in Appendix C.
Note: This requirement applies to any WEIM BAA
with existing access to RTM. No new access
provisioning needed in AIM, no updates to roles
needed in AIM.
Warning: “WEIM Operators are responsible for
ensuring this information is handled within
their own organizations consistent with
FERC’s Standards of Conduct for
Transmission Providers. The CAISO is not
requiring any additional attestations from
WEIM Operators or imposing additional
access controls within the BAAOP system.
Core
RTM RTD
RTPD
STUC
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 11 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
FAB
BRQ012
Transmission Resource Congestion
Within System (RTM), the RTD, RTPD, and
STUC UIs must display to CAISO and WEIM
Operators any constraint in the system that is
moving their resource and not just within their own
BAA.
Note: UI updates only for displaying existing-in-
application data that is not currently shown.
Note: See Mockup in Appendix C.
Note: This requirement applies to any WEIM BAA
with existing access to RTM. No new access
provisioning needed in AIM, no updates to roles
needed in AIM.
Warning: “WEIM Operators are responsible for
ensuring this information is handled within
their own organizations consistent with
FERC’s Standards of Conduct for
Transmission Providers. The CAISO is not
requiring any additional attestations from
WEIM Operators or imposing additional
access controls within the BAAOP system.
Core
RTM RTD
RTPD
STUC
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 12 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
FAB
BRQ013
Binding Transmission Constraints Flowgates
Within System (RTM), the RTD, RTPD, and
STUC UIs must display to CAISO and WEIM
Operators their BAA’s resources in the Binding
Transmission Constraints Flowgates” table (left
side).
Note: UI updates only for displaying existing-in-
application data that is not currently shown.
Note: See Mockup in Appendix C.
Note: This requirement applies to any WEIM BAA
with existing access to RTM. No new access
provisioning needed in AIM, no updates to roles
needed in AIM.
Warning: “WEIM Operators are responsible for
ensuring this information is handled within
their own organizations consistent with
FERC’s Standards of Conduct for
Transmission Providers. The CAISO is not
requiring any additional attestations from
WEIM Operators or imposing additional
access controls within the BAAOP system.
Core
RTM RTD
RTPD
STUC
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 13 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
FAB
BRQ014
Binding Transmission Constraints Flowgates
Within System (RTM) in the RTD, RTPD, and
STUC UIs, must have functionality for CAISO and
WEIM Operators to select any of their resources
from the left side of the table and on Constraints
Causing Congestion” table (right side).
Note: Add new column BAA” to Resource
Participation table.
Note: UI updates only for displaying existing-in-
application data that is not currently shown.
Note: See Mockup in Appendix C.
Note: This requirement applies to any WEIM BAA
with existing access to RTM. No new access
provisioning needed in AIM, no updates to roles
needed in AIM.
Warning: “WEIM Operators are responsible for
ensuring this information is handled within
their own organizations consistent with
FERC’s Standards of Conduct for
Transmission Providers. The CAISO is not
requiring any additional attestations from
WEIM Operators or imposing additional
access controls within the BAAOP system.
Core
RTM RTD
RTPD
STUC
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 14 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
FAB
BRQ015
Binding Transmission Constraints Flowgates
Within System (RTM), the RTD, RTPD, and
STUC UIs must display to CAISO and WEIM
Operators any constraint in the system that is
moving their resource and not just within their own
BAA.
Note: UI updates only for displaying existing-in-
application data that is not currently shown.
Note: See Mockup in Appendix C.
Note: This requirement applies to any WEIM BAA
with existing access to RTM. No new access
provisioning needed in AIM, no updates to roles
needed in AIM.
Warning: “WEIM Operators are responsible for
ensuring this information is handled within
their own organizations consistent with
FERC’s Standards of Conduct for
Transmission Providers. The CAISO is not
requiring any additional attestations from
WEIM Operators or imposing additional
access controls within the BAAOP system.
Core
RTM RTD
RTPD
STUC
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 15 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
FAB
BRQ016
Binding Transmission Constraints Nomograms
Within System (RTM), the RTD, RTPD, and
STUC UIs must display to CAISO and WEIM
Operators their BAA’s resources in the Binding
Transmission Constraints Nomograms” table (left
side).
Note: UI updates only for displaying existing-in-
application data that is not currently shown.
Note: See Mockup in Appendix C.
Note: This requirement applies to any WEIM BAA
with existing access to RTM. No new access
provisioning needed in AIM, no updates to roles
needed in AIM.
Warning: “WEIM Operators are responsible for
ensuring this information is handled within
their own organizations consistent with
FERC’s Standards of Conduct for
Transmission Providers. The CAISO is not
requiring any additional attestations from
WEIM Operators or imposing additional
access controls within the BAAOP system.
Core
RTM RTD
RTPD
STUC
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 16 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
FAB
BRQ017
Binding Transmission Constraints Nomograms
Within System (RTM) in the RTD, RTPD, and
STUC UIs, must have functionality for CAISO and
WEIM Operators to select any Nomograms from
the left side of the table and on Resource
Participation” table (right side).
Implementation note: Add new column BAA to
Resource Participation table.
Note: UI updates only for displaying existing-in-
application data that is not currently shown.
Note: See Mockup in Appendix C.
Note: This requirement applies to any WEIM BAA
with existing access to RTM. No new access
provisioning needed in AIM, no updates to roles
needed in AIM.
Warning: “WEIM Operators are responsible for
ensuring this information is handled within
their own organizations consistent with
FERC’s Standards of Conduct for
Transmission Providers. The CAISO is not
requiring any additional attestations from
WEIM Operators or imposing additional
access controls within the BAAOP system.”
Core
RTM RTD
RTPD
STUC
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 17 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
FAB
BRQ018
Binding Transmission Constraints Nomograms
Within System (RTM), the RTD, RTPD, and
STUC UIs must display to CAISO and WEIM
Operators any resource in the system that is
being moved due to congestion and not just within
their own BAA.
Note: UI updates only for displaying existing-in-
application data that is not currently shown.
Note: See Mockup in Appendix C.
Note: This requirement applies to any WEIM BAA
with existing access to RTM. No new access
provisioning needed in AIM, no updates to roles
needed in AIM.
Warning: “WEIM Operators are responsible for
ensuring this information is handled within
their own organizations consistent with
FERC’s Standards of Conduct for
Transmission Providers. The CAISO is not
requiring any additional attestations from
WEIM Operators or imposing additional
access controls within the BAAOP system.
Core
RTM RTD
RTPD
STUC
4.1.2 Business Requirements: External WEIM Commitment Override
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 18 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
ID#
Business Feature
Req. Type
Potential
Application(
s)
Impacted
FAB
BRQ030
External WEIM Commitment Override
System (RTM) within BAAOP, must have the
capability for external WEIM BA Operators to enter
commitment overrides directly in the RTM Market
UI.
Note: Currently, external WEIM entities call the
RTMO to request the commitment override and the
RTMO enters the override into the RTM via
BAAOP.
Note: This requirement applies to any WEIM BAA
with existing access to RTM. No new access
provisioning needed in AIM, no updates to roles
needed in AIM.
Core
RTM -
BAAOP
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 19 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
4.1.3 Business Requirements: System NET ITC Definitions
ID#
Business Feature
Req. Type
Potential
Application(s)
Impacted
FAB
BRQ050
System NET ITC Definitions (MF Definitions Only)
Internal ISO team to update definitions in
MasterFile for all existing WEIM entities.
Note: Definitions would be updated as
currently performed during onboarding WEIM
entities, in this case would be for all existing
entities.
Existing,
Business
Process
MF
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 20 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
4.1.4 Business Requirements: Dynamic ETSR Limits Safety Net
ID#
Business Feature
Req. Type
Potential
Application(s)
Impacted
FAB
BRQ040
Dynamic ETSR Limits Safety Net
This enhancement seeks to define and
introduce a safety net in the event the
Dynamic Limits Interface (DLI) has an issue
with send/receive payload or null values in
RTM.
CAISO is actively scoping this enhancement to
ensure WEIM alignment prior to proposing an
agreed upon solution.
Note: This item shall be more thoroughly
disclosed in a future External BRS posting.
Core
RTM - BAAOP
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 21 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
Appendix C: Display Mockup and Report
Questionnaire
Resource Congestion Mockup (BRQ010, BRQ011, BRQ012)
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 22 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
Binding Transmission Constraints Flowgates Mockup (BRQ013, BRQ014,
BRQ015)
Copyright 2024 California ISO
Doc ID: GNFDMDEHU6BB-46-53 Page 23 of 23
Technology
Template Version:
6.8
Document
Version:
1.0
WEIM FAB Enhancements Business Requirements Specification -
Planning
Date Created:
2/10/2024
Binding Transmission Constraints Nomograms Mockup (BRQ016, BRQ017,
BRQ018)